NASA is aiming to land astronauts on the Moon in 2028, after a planned crewed test flight in 2027 brings its Orion spacecraft together with lunar landers being developed by SpaceX and Blue Origin. The two-mission outline was described by NASA Administrator Jared Isaacman and other agency leaders at an October 23 briefing, according to a ScienceDaily report based on materials provided by NASA.

Under the plan, Artemis III would send four astronauts aboard Orion for a 14-day mission in Earth orbit. The crew would practice rendezvous and docking with test versions of both companies’ landers. NASA says these demonstrations are meant to check important spacecraft capabilities before Artemis IV attempts a landing. The orbital rehearsal is a planned test, not evidence that either lander is ready to carry a crew to the lunar surface.

The reported sequence starts with Blue Origin launching a test version of its Blue Moon lander into Earth orbit. Orion would then launch on NASA’s Space Launch System rocket and dock with Blue Moon. After separating, Orion would perform another docking maneuver with a test version of SpaceX’s Starship lunar lander. Practicing with both vehicles during one mission is intended to give NASA experience with their operations and reduce uncertainty ahead of the landing attempt.

For Artemis IV, NASA plans to send astronauts around the Moon aboard Orion and use a lander from either company to reach the surface. SpaceX’s approach calls for Starship to take on more propellant in Earth orbit before meeting Orion and traveling toward the Moon. Blue Origin’s plan uses additional propulsion stages to send its Blue Moon Mark 2 lander toward the Moon, where it would meet Orion in a relatively low lunar orbit. Both systems are still in development, and the report does not say which one NASA will use.

Keeping two potential landing systems in the plan gives NASA flexibility as development and testing proceed, the agency said. NASA is also considering two upper-stage options for the Artemis IV SLS rocket: the interim cryogenic propulsion stage already used by SLS, or an extended version of United Launch Alliance’s Centaur V stage. The agency said alternatives could help it respond to engineering challenges while preserving the broader schedule.

The report describes other efforts aimed at shortening preparations. NASA said hardware for Artemis III remained on schedule and that processing improvements had cut preparation timelines by about 50%. It also reported that agency engineers redesigned, manufactured and tested a critical rocket fuel-line component in five months. NASA said the work cost roughly one-tenth of an earlier estimate from an outside vendor. Those figures are NASA’s account of its progress; the report does not provide an independent assessment of the savings or schedule gains.

A lighter spacesuit is another part of the plan. NASA is working with Axiom Space on a “Sortie suit” for the first lunar surface excursions. The report says it weighs approximately half as much as Axiom’s larger primary suit. It is intended to help with early moonwalks and is not meant to replace the primary suit, which NASA plans to use for longer periods outside the spacecraft and more demanding surface activities.

The agency’s aims extend beyond a single landing. NASA says it wants to send crews on increasingly challenging expeditions near the Moon’s South Pole and establish an enduring human presence there. The experience gained from more complex lunar missions is also intended to help prepare for future human exploration of Mars. Isaacman described the timetable as an urgent effort to deliver outcomes “as quickly, safely, affordably, and successfully as possible.” These remain goals attached to a development and flight schedule; the account does not establish that the 2028 landing or longer-term presence is assured.